VER - Dagdelen Weir and HEPP, Turkey

The proposed project is located at Upper Ceyhan Basin and planned as a run of river type at operation water level 1111.40 and tailwater level 1095.00 m. Two turbines having a total installed capacity of 7.91 MW will utilize local hydropower resources to generate and feed electricity to the National Grid via 34.5 kV transformer in Doganköy Substation.

VALIDATION


Following all project documents

PDD

Publication Date:July 04, 2011

Final PDD
Validation Report